Does a one-sided phased array scan prove that the wind weld root was examined?
The short answer
Only if the approved technique demonstrates adequate coverage of the relevant root region from that access. Electronic beam steering can improve access, but the joint geometry, material and available scan positions still determine which regions and orientations were interrogated. A one-sided scan label does not establish adequate root coverage by itself.
Start with the joint geometry and access limits
Request the actual joint drawing, weld identification, material, accessible surface and the scan plan. FHWA’s phased array material describes using a steered beam to examine regions that can be hard to access in bridge work. That demonstrates a technique capability, not the qualified scope for a wind tower joint. Ask how the proposed beam paths reach the root without assuming that a color image represents the full weld volume.
Check the qualification and the actual scan record
The responsible inspector should identify the reference or demonstration that supports detection in the relevant region. Ask whether the actual scan positions, angles and coverage matched the approved plan. If restricted access prevented a needed probe position, record the remaining unexamined region. A completed record for the accessible side is not evidence that the opposite region was examined unless the demonstrated beam paths and sensitivity support that conclusion.
Reconcile missing coverage against the purchase requirement
Give the engineering reviewer the inspected volume, reportable indications, limitations and any approved complementary evidence. Do not replace the requirement with a headline percentage or transfer a qualified setup from a different weld geometry. Where the evidence does not cover the specified root, the owner can require a defined disposition before acceptance. Keep the actual joint and revision on the report so later work can distinguish a method limitation from an evaluated indication.