Does a weld inspection percentage tell a wind tower buyer which joints were examined?
The short answer
A percentage needs a defined population and method. It can refer to the count of joints, weld length or some other agreed basis. Ask which joints and areas were actually examined, how they were selected and what the acceptance plan says about the rest.
Ask what the percentage was counted against
The inspection record should identify the joint population and drawing revision. Sampling a portion of the length of one seam differs from inspecting a portion of all seams. The report should show where the examination starts and stops and what the numbers represent.
Use the supplier’s weld map to connect each report entry to the structure. If a label groups several joints under one name, request enough detail to identify the actual inspected locations.
Match the method to its documented scope
FHWA’s bridge welding guidance illustrates that visual and nondestructive methods address different discontinuities and can be assigned to different joint categories. A tower project has its own inspection plan and criteria. Confirm the method, coverage, accessible regions and limitations that apply to the offered assembly.
A completed examination on one accessible area does not establish what was examined on the other side of the joint. Identify any excluded areas and any supplementary method used.
Close the requirement against the agreed plan
Ask for the inspected joint list, method, results and disposition of findings. Check that sampling and any escalation after a finding followed the approved plan. Keep the difference between verified results and areas outside the sampling scope visible in the handoff. A single headline percentage is insufficient to resolve those details.