Can a switchboard design verification report release the individual wind project switchboard?
The short answer
Check both the design evidence applicable to the offered switchboard and the individual assembly’s routine verification record where required by the agreed specification. Design evidence addresses the assembly design and the conditions it represents. Routine evidence addresses the manufactured item identified in the supplier’s release records.
Check what design the reference covers
Identify the assembly type, drawings, construction details and relevant service conditions used in the design verification. Compare those details with the offered unit. Ask the supplier to explain how any different enclosure, internal arrangement or cooling option falls within the scope of the cited evidence.
Siemens describes design verification and routine verification as separate activities in its SIVACON low-voltage switchboard planning manual. Use that distinction when reviewing the applicable assembly specification and the scope agreed with the actual supplier.
Request the record for the supplied assembly
Where the purchase requires routine verification, request a record traceable to the serial number or other unique assembly identity. It should identify the applied procedure, the checks performed, the actual results and any resolved or open departures. A routine verification sheet bearing only a common product family name can leave the link to the supplied switchboard unresolved.
Ask the supplier to distinguish routine production evidence from any buyer witness activity. A witness can record what was observed without replacing the production records called for in the order.
Keep site checks in their own scope
Reconcile the supplier records with the equipment schedule and the identified switchboard before releasing the supplier milestone. For example, the installed switchboard may have site cables and external controls that were outside the manufacturer’s setup. List evidence needed for those interfaces under the commissioning plan. The purchase review should show who closes each design, production and site requirement.