Small wind / Buyer questions
Procurement and engineering handover
Can a wind component supplier reuse its first article inspection after moving production?
The short answer
Check what changed in the production process before applying the earlier first article inspection to output from the new location. A shared drawing revision establishes the design target. The first article record also depends on the manufacturing and inspection conditions that produced its results.
Compare the old and new production routes
Ask the supplier which operation moved, where the first affected lot will be made and whether the machine, fixture, program, material source or inspection setup changed. Establish which characteristics each changed operation can influence. Moving drilling to a second machine, for example, can affect the position of a mounting pattern even when the supplier uses the original drawing and nominal tool dimensions.
Identify the last lot covered by the old route and the first lot made under the new one. Separate any inventory produced using mixed routes until the supplier can identify the actual process for each affected item.
Choose the scope of additional inspection
The IAQG first article FAQ for the aerospace sector illustrates an assessment based on potential effects on fit, form or function when production moves. It treats move distance as a poor measure of that impact. Use the inspection terms agreed for the wind order and document the technical rationale for the scope chosen.
For a change limited to a mounting hole operation, the reviewer may ask for the affected drawing characteristics and the inspection setup. A wider change to several operations may call for a broader new first article.
Connect the decision to the first affected lot
Retain the original first article, the supplier change notice, the characteristic comparison and the approved scope of repeat checks. The new inspection record should identify the production route and the actual article checked. Identify who accepts that evidence and which lot may proceed. Keep the first article decision separate from any routine inspections that the purchase requires on later units.
Sources
Examples are illustrative. Confirm product-specific performance, compatibility and supply scope in the applicable documents.