Should a retrofit gateway replace a wind alarm's original time with the time it received the alarm?

Small wind / Buyer questions

Electrical retrofit interfaces

Should a retrofit gateway replace a wind alarm's original time with the time it received the alarm?

The short answer

Keep both times when the source provides them. The original time describes when the device recorded the event, while receipt time describes when a gateway or server obtained it. A controls retrofit that stores only receipt time can reorder alarms in a way that misleads later troubleshooting.

Account for buffered and delayed alarms

Consider a hypothetical communications interruption during which the wind controller records a trip and the site meter records a later loss of generation. If their records reach the server through different queues, the later event can appear first when the display sorts only by arrival. The OPC Foundation's event model distinguishes occurrence time from server receipt time, providing a useful example of how to represent both.

Preserve the limits of the original record

Device event time can also be uncertain if the source clock was unsynchronized or reset. Retain the source identity, original time field and clock quality information where available. Mark records with unavailable source time rather than assigning the server timestamp an unsupported meaning.

Check whether exported time is UTC or local time with an offset, and whether the retrofit changes timestamp precision. Two events stored at the same second may have an unknown order when the original device retained finer resolution or used a separate sequence counter.

Define what the handover export must show

Ask for a sample event file showing the equipment identifier, alarm code, original occurrence time, gateway receipt time and any missing-time indicator. Include buffered events in the agreed review, because ordinary live traffic may hide the effect of storage and replay. Clarify which field the operations dashboard uses to sort events and whether the original record remains available for engineering review. Specify that decision in the gateway quotation so a display redesign does not silently change the meaning of the alarm sequence.

Sources

Examples are illustrative. Confirm product-specific performance, compatibility and supply scope in the applicable documents.