Can a PLC load an older project from its memory card after a restart?
The short answer
Some controller configurations can load a stored project from nonvolatile memory under particular conditions. Rockwell's Logix documentation describes options that include loading on power-up for applicable controllers. The active program and the stored image can differ. A commissioning change that is active before a restart therefore needs separate evidence about what the controller will load after power returns. Confirm the actual device and policy before drawing a conclusion.
Identify both project states
Record the controller and firmware, approved running project, stored image identity and configured load condition. In a hypothetical service event a recent change is active, while a card still contains an older image. If the selected policy loads that image on power-up, the controller's post-restart state can differ from its pre-restart state. Preserve evidence for both states rather than assuming the card mirrors every online edit.
Check the approved restart observation
Ask the controls team what verification is appropriate for the actual equipment and authorized test conditions. Record the observed project identity and relevant functional behavior following an approved restart. Note any differences between manual restoration and automatic loading. Keep the test environment and actual installed policy visible so a bench result is not treated as proof of a different site configuration.
Maintain a traceable recovery baseline
Record which image is approved, when it was stored and how future changes will keep the relevant records aligned. If the load behavior is uncertain, identify the responsible reviewer and the evidence required. This gives the site a concrete way to investigate unexpected reversion without changing a running program or load policy outside its approved controls process.
Sources
Examples are illustrative. Confirm product-specific performance, compatibility and supply scope in the applicable documents.