Does an MV cable withstand pass supply the partial-discharge evidence requested for a wind site?
The short answer
A withstand pass establishes the result of the specified voltage exposure. A requested partial-discharge assessment needs its own recorded diagnostic information. BAUR describes PD diagnostics for faults in cables and accessories, including joints and terminations, and combines diagnostics with withstand testing in its monitored approach. Apply that distinction to an installed MV site circuit when its acceptance plan requests both.
State the diagnostic deliverable before comparing reports
Ask which cable section and accessories the requirement covers and which diagnostic outputs the specialist must deliver. BAUR identifies discharge location, level and inception or extinction behavior among its available information. The project specification should identify the applicable interpretation and reporting requirements for the actual cable system. Keep the agreed method and equipment configuration with the acceptance schedule so the supplier can quote the intended scope.
Check what the submitted result actually contains
In a hypothetical wind-site connection, a contractor submits a withstand certificate for a screened MV feeder containing new joints. The purchase scope also requests a PD assessment of that installed system. The buyer checks for the corresponding diagnostic record and the specialist’s interpretation of the joint locations. A certificate reporting the voltage exposure alone leaves that separately requested deliverable open. The agreed cable specification and specialist’s interpretation determine the acceptance decision for this particular installation.
Retain the specialist’s decision and the configuration
Keep circuit identity, joint schedule, test conditions, observations and the qualified reviewer’s disposition together. Ask the specialist to explain any measurement limitation that affects the required acceptance decision. If the contract calls for additional assessment, identify the evidence still needed and its owner. Record which requirements are closed by each document so a later accessory replacement can be evaluated against the actual accepted cable system and its documented diagnostic baseline.
Sources
Examples are illustrative. Confirm product-specific performance, compatibility and supply scope in the applicable documents.